The Technical office module is responsible for two things: controlling engineering documents (on the ISO 19650 standard) and execution quality. And it is the engine behind the "gates" you met earlier — the approved sample is a condition for purchasing (Ch.6), and a non-conformance holds back the payment certificate (Ch.4).
/technical-office, the "Technical office" menu). It has 11 registers (tabs), the default being "Overview". Editing is for editors (owner/admin/manager), and the viewer only reads.02 The document register and transmittals
The foundation of the module: a document library controlled by its revisions, and a numbered distribution register that links them to whom they were sent.
- Document register
- The drawings and documents under control, with their revisions. For each document: number · title · discipline · type (drawing/specification/calculations/report/BIM model…) · suitability code (ISO 19650: from S0 "work in progress" to A1 "approved-published") · CDE status (work in progress / shared / published / archived) · review status. The New revision button creates a new current copy, serialises it above the previous one, and archives the old one automatically. And the Current revisions only toggle hides the superseded ones.
- Transmittals
- Numbered issue/distribution records (TR-…) that link document revisions to one another: the subject, the recipient, the purpose (for approval/for review/for information/for construction/for records), the method, and the status (draft/issued/receipt confirmed) — with a PDF cover sheet ready to send.
03 Technical submittals
The Technical submittals tab: material submittals and shop drawings with the consultant's review cycle and return codes — and it is the core on which the procurement gate depends.
- Types and fields
- Types: material submittal / shop drawing / sample / method statement / prototype. Each submittal has an automatic number (SUB-…), a specification item, a linked document, a linked catalog material, the contractor and consultant, submission/required/return dates, and the return code.
- Return codes
- A approved · B approved with comments · C revise and resubmit · D rejected · (under review). Only A and B count as "approved" and open the purchasing of that material (Section 6). The Resubmit button opens a new revision and closes the previous one.
- The critical link
- Linking the submittal to the catalog material is the key by which procurement recognises "does this material have an approved sample?". Without the link, the gate does not open.
04 Requests for information and inspection
Two daily registers: technical queries directed to design/the consultant, and inspection requests for works and materials.
- Requests for information (RFI)
- A technical query with an automatic number (RFI-…), a priority and a cost/time impact. The cycle: Open → Answered → Closed (and void). The "stops work / holds the payment" option reveals the subcontractor and held amount fields — so the value of the works concerned is held in the client's payment certificate and payment of the subcontract certificate is prevented, and the hold is lifted as soon as it is answered/closed (Section 6).
- Inspection requests (IR/WIR)
- A request to inspect works or materials with an automatic number (IR-…): the type, the location, the work reference / bill of quantities item (text), the inspector/consultant, and the result (approved / approved with comments / rejected / pending), and the status (requested/scheduled/inspected/closed). A non-conformance report can be linked to an inspection.
05 Non-conformance (NCR)
The Non-conformance tab: NCR reports on the ISO 9001 style to record deviations, determine the disposition and close them — and they are the quality gate with the strongest impact on the money.
- Fields and cycle
- An automatic number (NCR-…), a severity (minor/major/critical), a source (inspection/audit/the client/internal), a description, the disposition (rework/repair/accept as is/reject/concession), a root cause and a corrective/preventive action, and a responsible party and a due date. The cycle: Open → In progress → Closed.
- The held value
- The subcontractor and held value fields: as long as the NCR is open or in progress, this value is excluded from the client's payment certificate and payment of the subcontract certificate is prevented (Section 6).
- The material return bridge
- A "Material return" section: you specify the source purchase order, the material and the rejected quantity, and the Create return button creates a vendor return (draft) that you post from Procurement › Returns (Ch.6).
06 The gates: how the technical office protects the money
Here is the module's great value: its registers are not documentation only, but binding controls over procurement and payment certificates.
- The procurement gate
- When awarding a request for quotes or saving a purchase order, material line items that do not have an approved sample (code A or B) linked to the catalog material are not accepted — and hints appear on the line item: ✓ Sample approved (code …) or ⚠ No approved sample. Services and items without a catalog are exempt.
- The quality hold on payment certificates
- The value of any open NCR or blocking RFI (with a held amount) is excluded from the approved amount in the client's payment certificate — with a "quality hold" tag — and approval/payment of the subcontract certificate against that contractor is prevented. And the hold is lifted automatically as soon as the NCR is closed or the RFI is answered/closed.
07 Technical changes, correspondence and handover
Three registers complete the project cycle: the engineering change that feeds the commercial side, correspondence tracking, and the final handover file.
- Technical changes
- An engineering change (design/site instruction/value engineering…) with a cost, sale and time impact. The Create commercial change order button generates a variation order (VO) in the commercial module and links it — so after its approval the adjusted contract value and revenue enter (Ch.4). (Requires specifying a project.)
- Correspondence
- Incoming/outgoing with an automatic number (LTR-…), with tracking of "whose court the ball is in" (us/them/closed) and reply dates — to manage your claims and notices with the parties.
- Method statements and handover
- Method statements: work procedures with a risk level and approval. And handover: the project closeout list (As-built drawings, operation and maintenance manuals, warranties, certificates) with a status and completion percentage and a PDF file.
08 Permissions — and the summary
| Action | Owner | Admin | Manager | Viewer |
|---|---|---|---|---|
| View the eleven registers (read) | ✔ | ✔ | ✔ | ✔ |
| Documents and transmittals — create/new revision | ✔ | ✔ | ✔ | ✖ |
| Submittals/RFI/inspection/NCR — create, review and close | ✔ | ✔ | ✔ | ✖ |
| The bridges — change order · material return | ✔ | ✔ | ✔ | ✖ |
All registers are for editors (owner/admin/manager) in creation, review and closure, and the viewer only reads. Note: "the consultant/inspector" in the forms is a text field, not a binding role within the system — so the return code, the inspection result and the closure of the NCR are set by any editor.